缩略词 | 中文说明 | 英 文 说 明 |
AC | 交流(电) | Alternating Current |
ACC | 无意见接收 | Accepted Without Comment |
AEN | 带意见接收 | Accepted With Comment |
AIA | 议标协议 | Award Intention Agreement |
AL | 铝 | Aluminum |
AMS | 行政事务管理系统 | Administration Management System |
ANSI | 美国国家标准协会 | American National Standards Institute |
ASME | 美国机械工程师学会 | American Society of Mechanical Engineers |
ASTM | 美国材料试验学会 | American Society for Testing and Materials
|
ATP | 开工令 | Authorization to Proceed |
AWN | 额外工作通知 | Additional Work Notice |
AWS | 美国焊接协会 | American Welding Society |
B/L | 装船提单,运货证书 | Bill of Landing |
BCL | 回填土检查单 | Backfilling Check List |
BF | 扁钢 | Flat Bar |
BHO | 厂房移交 | Building Hand Over |
BNI | 核岛配套设施 | Balance of Nuclear Island |
BO | 隔离办 | Blocking Office |
BOD | 董事会 | Board |
BOP | 电站配套设施 | Balance of the Plant |
BOQ | 工程量表 | Bill of Quantities |
BS | 英国标准 | British Standard |
BSI | 英国标准协会 | British Standard Institute |
BTS | 技术规范 | Book of Technical Specification |
BW | 对接焊,对接焊焊缝 | Butt Weld |
BWR | 沸水堆 | Boiling Water Reactor |
C&F | 离岸加运费价格 | Cost and Freight |
CAE | 竣工状态(文件管理用语) | Certified as Executed |
CAR | 纠正措施报告(质保用语) | Corrective Action Report |
CCC | 货物状态证书 | Cargo Condition Certificate |
CCL | 灌浆检查单 | Concreting Check List |
CCP | 商务变更建议 | Contractual Change Proposal
|
CEMDS | 设备或材料在现场交货条件 | Condition of Equipment or Material upon
Delivery on-Site |
CEAR | 建筑安装工程一切险 | Construction & Erection all Risks |
CFA | 可以使用 | Clear for Action |
CFC | 可供施工使用(文件状态) | Certified For Construction |
CFT | 冷态功能实验 | Cold Function Test |
CFT-RVO | 冷试-压力容器开盖 | Cold Function Test - Reactor Vessel Open |
CHOC | 土建交接证书 | Civil Hand Over Certificate |
CI | 常规岛 | Conventional Island |
CIF | 到岸价格 | Cost, Insurance & Freight |
CIN | 设备问题处理通知 | Component Intervention Notice |
CLP | 中华电力有限公司 | China Light & Power Co Ltd |
CM | 施工经理 | Construction Manager |
CNEIC | 中国原子能工业公司 | China Nuclear Energy Industrial Co |
CNNC | 中国核工业总公司(中核总) | China National Nuclear Corporation |
CO | 商业运行 | Commercial Operation |
COD | 商业运行日期 | Commercial Operation Date |
CP | 建造许可证 | Construction Permit |
CPL | 符合性消缺单 | Conformity Punch List |
CPT | 临界前冷试 | Cold Precritical Test |
CQU | 电厂质量放行 | Plant Quality Release |
CRF | 澄清问题申请单 | Clarification Request Form |
CRI | 临界 | Criticality |
CRTC | 中国汽车运输总公司 | China Road Transportation Company |
CS | 碳钢 | Carbon Steel |
CTT | 安全壳试验 | Containment Tests |
CW | 土建工程 | Civil Work |
CWJ | 焊接接头目录 | Catalog of Welded Joint |
DCM | 调试(日)例会 | Daily Commissioning Meeting |
DCR | 设计变更请求 | Design Change Request |
DDD | 国内直拨(电话) | Domestic Direct Dialing |
DEN | 设计修改通知 | Design Evolution Notice |
DES | 描述性(文件类别) | Description |
DMS | 文件资料管理系统 | Document Management System |
DOC | 资料中心 | Documentation Center |
DP | 着色探伤 | Dye Printing |
DPS | 大亚湾公安分局 | Daya Bay Public Security Branch |
DR | 偏差项报告 | Deviation Reports |
DS | 设计规范(文件编码用语) | Design Specifications |
DWG | 图纸 | Drawing |
ECC | 设备状态证书 | Equipment Condition Certification |
EDF | 法国电力公司 | Electricite De France (法语) |
EEC | 安装竣工证书 | End of Erection Certification |
EESR | 安装竣工报告 | End of Erection Status Report |
EIR | 环境影响报告 | Environmental Impact Report |
EMC | 制造完工合格证 | End Manufacturing Certificate |
EMP | 机电(工程)包 | Electro Mechanical Package |
EMR | 制造完工报告 | End of Manufacturing Report |
EMS | 电气管理系统 | Electrical Management System |
ENG | 技术实施细则 | Engineering Procedure Manual |
EOMM | 设备运行维修手册 | Equipment Operation and Maintenance Manual |
EOMR | 设备出厂报告 | End of Manufacturing Report |
EP | 应急准备 | Emergency Preparedness |
EPT | 性能试验结束 | End of Performance Test |
ERFS/EESR | EESR签字后保留项目跟踪
文件 | Reservation Follow-up Sheet after EESR |
ETF | 执行跟踪档案 | Execution Tracing File |
FAC | 最终验收证书 | Final Acceptance Certificate |
FBR | 快中子反应堆 | Fast Breader Reactor |
FC | 按文件作施工准备 | For Construction |
FCN | 现场变更通知 | Field Change Notice |
FCO | 现场更改单 | Field Change Order |
FCR | 现场修改申请 | Field Change Request |
FD | 燃料交付 | Fuel Delivery |
FL | 装料 | Fuel Loading |
FOB | 离岸价格 | Free on Board |
FP | 动火票 | Fire Permit |
FPW | 全透焊,全透焊焊缝 | Full Penetration Weld |
FRA | 法国法马通公司 | Framatome |
FS | (经验)反馈单 | (Experience) Feedback Sheet |
FSAR | 最终安全分析报告 | Final Safety Analysis Report |
FSS | 全范围模拟机 | Full Scope Simulator |
FTG | 岗位培训导则 | Function Training Guide |
FU | 供使用(文件状态) | For Use |
FW | 装修工程,收尾工程 | Finishing Work |
FW | 现场焊 | Field Weld |
FW | 角焊缝,填角焊焊缝 | Fillet weld |
GAF | 货物验收单 | Goods Acceptance Form |
GCR | 气冷反应堆 | Gas Cooled Reactor |
GCR | 网控室 | Grid Control Room |
GEC | 通用电气公司(英国) | General Electric Corp |
GEC/A | 通用电气/阿尔斯通公司 | GEC Alsthom |
GEPB | 广东省环保局 | Guangdong Environmental Protection Bureau |
GEPEC | 广东火电 | |
GGPC | 广东省电力总公司 | Guangdong General Power Company |
GMAW | 气体保护金属极电弧焊 | Gas Metal Arc Welding |
GN | 说明书(文件编码用语) | General Notes |
GNIC | 广东核电投资有限公司 | Guangdong Nuclear Power Investment CoLtd |
GNPGSC | 广东核电服务总公司 | Guangdong Nuclear Power General Services Co |
GNPJVC | 广东核电合营公司 | Guangdong Nuclear Power Joint Venture Co,Ltd |
GNRB | 核安全评审委员会 | General Nuclear Review Board |
GQS | 通用质量规范 | General Quality Specifications |
GTAW | 气体保护钨极电弧焊 | Gas Tungsten Arc Welding |
GTC | 合同总条款 | General Terms and Conditions |
HFT | 热态功能试验 | Hot Functional Test |
HKSAR | 香港特别行政区 | Hong Kong Special Administrative Region |
HO | 总公司(总部) | Head Office |
H-Point | 停工待检点 | Hold Point |
HPT | 临界前热试 | Hot Precritical Test |
HVAC | 暖通空调 | Heating Ventilation and Air Conditioning |
IAEA | 国际原子能机构 | International Atomic Energy Agency |
IDD | 国际直拨(电话) | International Direct Dialing |
IEF | 内部经验反馈 | Internal Experience Feedback |
II | 独立检查 | Independent Inspection |
ISI | 在役检查 | |
I | 国际标准化组织 | International Standard Organization |
I | 等轴图 | Iso |
I14000 | 国际环境管理标准 | |
ITT | 招标书 | Invitation to Tender |
JVC | 合营公司 | Joint venture Co Ltd |
KAF | 关键日工作进度表(格式) | Keydate Achievement Form |
Lab | 试验室 | |
LANPC | 岭澳核电有限公司 | |
LBP | 大口径管 | |
LCE | | |
LIC | 执照 | Lience |
LOI | 意向书 | Letter of Intent |
LPT | 液体渗透试验 | Liquid Penetration Test |
LT | 泄漏试验,紧密性试验 | Leakage Test; Leak Test |
LIB | 执照申请处 | Lience Application branch |
LWGR | 轻水石墨(反应)堆 | Light-Water Graphite Reactor |
MCR | 主控室 | Main Control Room |
MF | 缩微胶片 | microfilm |
MH
| 工时数 | Man-hours |
MIN | 监督信息通知 | Monitoring Information Notice |
MQ | 材料催交 | Material Query |
MQP | 主质量计划 | Master Quality Plan |
MRF | 材料申请单 | Material Request Form |
MSR | 汽水分离再热器 | Moisture Separtor Reheater |
MSS | 材料提交单 | General Service Section |
MSTM | 整体螺栓拉伸机 | Multi-Stud Tensioning Machine |
MT | 磁粉检验,磁粉探伤 | Technical Assistant Section |
MTR | 材料转移申请 | Material Transfer Request |
NA | 不适用,不要求 | Magnetic Particle Test |
NC | 不符合项 | Not Applicable |
NCC | 核回路清洗 | Non Conforming Item |
NCR | 不符合项报告 | Nuclear Circuit Cleaning |
NDE | 无损检验 | Non Conformance Report |
NDT | 无损探伤 | Non Destructive Examination |
NEPC | 东北电建 | Non Destructive Test |
NFC | 通知施工 | Northeast Electrical Power Construction Co |
NFU | 宣布可用 | Notified for Construction |
NI | 核岛 | Notified for Use |
NNSA | 国家核安全局 | Nuclear Island Erection (Branch) |
NPS | 美国标准直管螺纹 | National Nuclear Safety Administration |
NPT | 美国标准锥管螺纹 | American Standard Straight Pipe Thread |
NQR | 与质量无关的 | American Standard Taper Pipe Thread |
NRC | 核管会(美国) | Non Quality Related |
NS | 核安全 | Nuclear Regulation Committee |
NSSS | 核蒸汽供应系统 | Nuclear Safety |
NTR | 无可报告 | Nuclear Steam Supply System |
NUSS | 核安全标准计划 | Nothing to Report |
OA | 办公自动化 | Nuclear Safety Standards Schedule |
OAC | 氧乙炔切割 | Office Automatic |
OAW | 氧乙炔焊 | Oxyacetylene Cutting |
OHO | 全面移交 | Contract & Supply Branch |
OJT | 在岗培训 | Overall Hand-over |
ON | 观察通知 | Observation Notice |
OPE | 运行工程师 | Occupational Medical Service |
OPI | 设备开箱检查 | Open Package Inspection |
OSR | 未完成的保留项 | Outstanding Reservation |
OT | 遗留任务,未完成项 | Outstanding Reservation |
PWR | 压水堆 | Outstanding Reservation |
PAC | 临时验收证书(合同用语) | Outstanding Reservation |
PAC | 等离子切割 | Outstanding Reservation |
PAF | 采购申请单 | Outstanding Reservation |
PCC | 包装状态证书 | Outstanding Reservation |
PCC | 部分完成证书 | Outstanding Reservation |
PCN | 电厂变更通知单 | Plant Change Notice |
PDI | 工程文件(文件类别) | Projects Documents |
PDP | 工程指导计划 | Project Directing Plan |
PEN | 部分试验完成,有偏差 | Partial Test Completion with Deviation |
PHT | 焊后热处理 | Postweld Heat Treatment |
PHWR | 重水(慢化、冷却)反应堆 | Pressurized Heavy-Water Moderated and Cooled Reactor |
PICC | 中国人民保险公司 | People's Insurance Co of China |
PIM | 工程接口(管理)程序 | Project Interface Management |
PO | 采购定单 | Purchase Order |
PRE | 征求意见稿 | Preliminary for Comments |
PS | 工程服务 | Project Service |
PSA | 概率安全评估 | Probabilistic Safety Assessment |
PSAR | 初步安全分析报告 | Preliminary Safety Analysis Report |
PSI | 役前检查 | Pre-Service Inspection |
PWN | 追加工作通知 | Plant Work Notification |
PWT | 产品焊缝试件 | Production Weld Test Coupon |
PWTCR | 产品焊缝试件报告 | Production Weld Test Coupon Report |
QA | 质量保证 | Quality Assurance
|
QADP | 质量保证文件数据包 | Quality Assurance Data Package |
QAM | 质保手册 | Quality Assurance Manual |
QAP | 质量保证大纲 | Quality Assurance Program |
QASR | 质量监督报告 | Quality Assurance Surveillance Report |
QC | 质量控制,质检 | Quality Control |
QCE | 质检工程师 | Quality Control Engineer |
QDS | 技术评定数据表 | Technical Qualification Data Sheet |
QNC | 非质量级别 | Quality Non-Classified |
QOM | 质量管理手册 | Quality Organization Manual |
QP | 质量计划 | Quality Plan |
QPM | 质量计划管理 | Quality Plan Management |
QR | 与质量有关 | Quality Related |
QS | 质量监督 | Quality Surveillance |
QSDR | 质量监督缺陷报告 | Quality Surveillance Deficiency Report |
QSDR | 质量监督偏差报告 | Quality Surveillance Deviation Report |
QSP | 质量安全计划 | Quality Safety Plan |
QSR | 与质量及(核)安全有关的 | Quality and Safety Related |
QTCWPDS | 用于评定试件的焊接工艺
数据单 | Welding Procedure Data Sheet for Qualification
Test Coupon |
RCCM | | Design & Construction Rules for Mechanical Components of PRW Nuclear Island |
RCR | 保留项消除申请 | Reservation Clear Request |
REF | 参考 | reference |
REV | 修改,修改版 | revision |
RF | 突面法兰,凸面法兰 | RAISED FACE FLANGE |
RFC | 试验不合格,需重作 | TEST REFUSED, TO BE REPERFORMED |
RFC | 退回改正(工程文件用语) | RETURN FOR CORRECTION |
RFC | 待重新呈报(文件批复) | |
RFI | 已准备好可以实施 | READY FOR IMPLEMENTATION |
RIN | 基准标识号 | REFERENCE IDENTIFICATION NUMBER |
RP | 辐射防护 | |
RP | 固定资产 | REAL PROPERTY |
RS | 滚动计划 | Roll Schedule |
RT | 射线探伤 | radiograph test |
RWL | 剩余工作清单 | |
SAR | 安全分析报告 | |
SBP | 小口径管 | |
SCAR | 重大纠正措施要求单 | |
SCS | 系统完工计划 | |
SDM | 系统设计手册 | |
SEPC | 山东电建 | |
SEPC-NP | 山东电建工程公司-核电 | |
SEPP | 标准安装程序包 | |
SER | 重大事件报告 | SIGNIFICANT EVENT REPORT |
SES | 供应商评审表 | SUPPLIER EVALUATION SHEET |
SI | 现场指示书 | Site Instructions |
SL | 供货边界 | Supply Limit |
SMAW | (气体)保护金属极电弧焊 | Supply Limit |
SPM | 整定值手册 | Set Point Manual |
SPSB | 深圳供电局 | Shenzhen Power Supply Bureau |
SPV | 第二方验证 | Second Party Verification |
SR | 供应要求(申请)单 | Supply Request |
SR | 重大事件报告 | Significant Incident Report |
SS | 值长 | Shift Supervisor |
SS | 不锈钢 | Stainless Steel |
SSA | 付值长 | Shift Supervisor Assistant |
SSP | 专门监督计划 | Special Surveillance Plan |
ST | 现场施工进度安排 | On Site Work Schedule |
STC | 现场调试委员会 | Site Testing Committee |
SUM | 调试经理 | Startup Manager |
SUT | 调试启动队 | Start Up Team |
SW | 承插焊,插套焊 | Socket Weld |
TA | 技术适应性修改 | Technical Adaptation |
TAC | 完全接受 | Total Acceptance |
TDD | 技术设计室 | Technical Design Office |
TEN | 完全接受,注明的除外 | Technical Design Office |
TFD | 水压试验流程图 | Test Fluid Drawing
|
TIG | 气体保护钨极电弧焊 | Tungsten Inert Gas Arc Welding |
TOB | 隔离移交 | Takeover for Blocking |
TOC | 技术待召 | Technical On Call |
TOM | 维修移交 | Take Over for Maintenance |
TOTO | 临时运行移交 | Take Over for Maintenance |
TQ | 培训和资格评定 | Take Over for Maintenance |
TQC | 全面质量管理 | Total Quality Control |
TQP | 典型质量计划 | Typical Quality Plan |
TR | 试验报告 | Test Report |
TRAS | 试验报告分析单 | Test Report Analysis Sheet |
TS | 技术支持 | Technical Support |
TS | 试验负责人 | Test Supervisor |
TS | 技术规范 | Technical Specifications |
TS/PQR | 焊接工艺评定报告技术
规程 | Technical Specification for Welding Procedure
Qualification Report |
TS/PWTCR | 产品焊缝试件报告技术
规程 | Technical Specification for Production Weld
Test Coupon Test |
TS/WQR | 焊工评定报告技术规程 | Technical Specification for Welder Quali-
fication Report |
TSA | 技术服务协议 | Technical Service Agreement |
TSD | 临时专用设施 | Temporary Special Device |
TSI | 临时监督指令 | Temporary Surveillance Instruction |
U | U型钢 | U Irons |
UCC | 机组完工证书
| Unit Completion Certificate |
UCD | 机组完工日期 | Unit Completion Date |
UES | 意外事件单(调试队发) | Unexpected Event Reports |
UT | 超声探伤 | Ultrasonic Test |
VFC | 已验证可施工 | Valid for Construction |
VFP | 已验证可预制 | Verified for Prefabrication |
VFT | 已验证可试验 | Valid for Test |
VO | 变更指令(合同用语) | Variation Order |
VT | 外观检验,目检 | Visual Examination(Inspection) |
WAS | 材料(设备)领用单 | Withdrawal Authorization Sheet |
WDP | 焊接数据包 | Welding Data Package |
WE | 带附件 | With Enclosure |
WF | 工作文件 | Work File |
WFQC | 焊接质量跟踪管理
| Welding Follow Up and Quality Control |
WG | 线规 | Wire Gauge |
WN-RF | 焊颈突面法兰 | Welding Neck-Raised Flange |
WNF | 焊颈法兰 | Welding Neck Flange |
WOA | 不带(无)附件 | Without Attachment |
WOE | 不带附件 | Without Enclosure |
W-Point | 见证点 | Witness Point |
WP | 工作计划 | Work Plan |
WPQ | 焊接工艺评定(注AMSE
标准称之为焊接程序评定) | Welding Procedure Qualification |
WPQR | 焊接工艺评定报告 | Welding Procedure Qualification Report |
WPQT | 焊接工艺评定试验 | Welding Procedure Qualification Test |
WQ | 焊工评定,焊工资格考评 | Welder Qualification |
WQDS | 焊接工艺数据表 | Welding Procedure Data Sheet |
WQR | 焊工评定报告 | Welder Qualification Report |
WQT | 焊工评定试验 | Welder Qualification Test |
WR | 工作申请 | Work Request |
WS | 工作负责人 | Work Supervisor |
WSL | 施工队长 | Work Section Leader |